[Construction Case] Short-term Correction: Certain Food Warehouse Void Filling Work

Upcon construction method using rigid polyurethane foam! Introducing a case where a cavity was corrected in three days.

We would like to introduce a case of "void filling work" conducted at a certain food warehouse in Kanagawa Prefecture. Using the Upcon method, which allows for the filling of voids that developed under the floor with polyurethane resin in a short period, we corrected a maximum void of 270mm (with a construction area of approximately 171m2) in just three days. After the resin filling, we checked the filling condition with a CCD camera and used non-shrink mortar to seal the injection holes. 【Case Overview】 ■ Construction Area: Approximately 171m2 ■ Maximum Void Size: 270mm ■ Location: A certain food warehouse in Kanagawa Prefecture ■ Construction Period: 3 days *For more details, please refer to the PDF document or feel free to contact us.

  • Renovation and repair methods
  • Ground foundation construction method
  • Civil Engineering Method

Added to bookmarks

Bookmarks list

Bookmark has been removed

Bookmarks list

You can't add any more bookmarks

By registering as a member, you can increase the number of bookmarks you can save and organize them with labels.

Free membership registration